Region(s):
Impasse Cite Garibou, Bernardin de Saint Pierre Street, Bait Ul Noor Street and along Bernardin de St. Pierre in direction of Cipaye Brulee
Length of Sewer:
3.2 km of sewer and Construction of 1 Pumping Station
No of House Connections:
200
Funding:
Government of Mauritius
Status:
10 % Completed. Awarded to Serveng Co. Ltd on 4 September 2024
Chamarel
60 m
16
Project is under DLP
The project covers roads along Claude Delaitre, Morcellement Raffray & Morcellement Le Roc
Contract allocated to Gamma Construction Ltd on 25 September 2023, 1.5 km reinstated out of 10 km
Avenue Sivananda (Opposite Vacoas Market)
105m of sewer diversion works
Contract awarded to Serveng Ltd on 03 July 2023
Pointe Aux Sables, Terrasson, Petit Verger, & Environs
3000
Contract awarded to JV Scene-Ries Consult Ltd/ Afri-Coast Consulting Engineers (Pty) Ltd on 12 April 2023.
Morcellement Goolamally and environs, Terre-Rouge
1.35 km of sewer
Around 160 nos
Contract awarded on 30 December 2022
Residence Vallée des Prêtres and part of Bernardin de St Pierre Road
1.7 km of sewer (rehabilitation/upgrading works)
280
In Progress
La Source- Quatre-Bornes, R.Ollier – Belle-Rose & Candos
3,805 m of main sewer / 3,450 m of lateral sewer (La Source - Quatre-Bornes & Candos)
510
Contract awarded on 12 May 2022
La Ferme, Bambous
3.5 Km of sewer
Around 275
Contract awarded to Serveng Ltd on 04 July 2023
Rodrigues
To be known upon completion of the Feasibility Study and Detailed Design